At Friday’s city commissioners meeting, there was an update on the Lyle Road project by Will Nedbalek, CEC.
This project began mid-January of this year and will continue into the spring of next year.
As of now, workers are 85 percent through their time allotted to finish the project and 60 percent through the money for the project — which puts the project behind schedule as they were given 380…